Development and application of megawatt closed mechanical drive tester
LIANG Xin-wen
YAN Huan-jing
WANG Qi-hun
SHI Quan-suo
CAO Jin-shui
FAN Shi-Yao
Abstract:The existing power closed mechanical drive tester of high-power gear box required large grid capacity and high energy consumption.Under the premise of no rebuilding the grid and without prejudice to normal production,Shanxi Pingyao Reducer Co.,Ltd.upgraded the mechanical transmission test-bed,from an original 250 kW electric closed cycle to a 2000 kW mechanical one.The new test-bed is of double to more than three times energy saving,system security and loading accuracy are better than those before.
Keywords:load test standtest bedenergy saving
Publication Date:2017-01-01
Online Publishing Date:2025-08-15(First online date of this platform, not the publication date of the document)
Pages:3( 9-11 )