Determination of designed production capacity in feasibility study report of mine
WANG He-de
Abstract:Mine feasibility study report shall firstly determine the designed production capacity of the approved master plan of mining area, then elaborate whether there are significant changes in mine external construction and resource conditions, if there are, analyze the possible influences on design production capacity. The paper points out that, at least three adjacent schemes shall be compared, including the approved overall designed production capacity. After comprehensive analysis of the main factors affecting the design and production capacity of mine, the recommended mine design and production capacity is proposed.
Keywords:designed production capacityresource reserveservice lifetechnical conditioncoal market
Publication Date:2016-01-01
Online Publishing Date:2025-08-15(First online date of this platform, not the publication date of the document)
Pages:3( 48-50 )