Initial platform construction of belt conveyor in open-pit mine dump
WU Jianyi
YANG Jianming
JIN Pengqing
QIU Chunfu
Abstract:The article combined with dumping process innovative scheme implement results in Xiaolongtan Open-pit Mine, in 1415 platform ascending segment to 1440 platform, using 912 belt conveyor to construct the initial platform of belt conveyor in 1440 platform, and makes full use of dumping machine moving forward to make the belt conveyor extended to the maximum length, which achieves a complete belt conveyor initial platform. The scheme saved the transportation cost for enterprise, realized the two platforms alternating dumping, and effectively relieved the dumping pressure.
Keywords:open-pit mine dumpascending partinitial platform of belt conveyor
Publication Date:2016-01-01
Online Publishing Date:2025-08-15(First online date of this platform, not the publication date of the document)
Pages:3( 32-34 )

ISSN:1671-9816
Year, Vol.(Issue):2016,31(11)