YIN Zhengwen
Abstract:In order to improve the reliability of semi-continuous dumping system in Buzhaoba Open-pit Mine Longqiao dump and ensure the ability of stripping and transportation in open-pit mine, the mine innovatively designs dumping plough dumping technology ascending material distribution system ,and uses the old trucks to make self-moving belt conveyor, which increases the dumping radius of dumping plough. The whole innovation scheme simplifies the ascending method of dumping technology under the complex terrain of hillside dump, which greatly improves effective operating time of system, reduces initial engineering quantity of dumping line and saves production cost.
Keywords:open-pit minehillside dumpcomplex basementascending
Publication Date:2016-01-01
Online Publishing Date:2025-08-15(First online date of this platform, not the publication date of the document)
Pages:5( 49-52,56 )