A Combined Application and Practice of Multiple Support Techniques in Roadway Heading Passing through F 108-1 Fault
CHEN Gang
WANG Ru-qiu
WANG Meng
Abstract:This paper introduces the Guqiao Mine south tape machine (two) ,F108-1 normal fault driv-ing ,the working face advance grouting and lag grouting two grouting ,anchor cable network active sup-port ,U type shed rigid support and grouting anchor cable supporting three support combination by the way ,optimization of construction scheme ,reasonable organization of construction work ,ensure the Gu-qiao Mine production ,reduce roadway repair quantity ,improve the service life of roadway and achieved good technical and economic benefit.
Keywords:roadway excavationpassing through faultmulti-supportcombined application