Optimization Design of 220kV Outgoing Line Steel Frame in Anyang Power Plant Extension Project
Abstract:Analysis of the data cooperation in steel frame design between electric and civil construction specialty. According to the complicated environment of Anyang power plant extension project, general methods and something should be paid attention in electric design which shall be for reference are summarized.
Keywords:steel framedata cooperationoptimization design
Publication Date:2011-01-01
Online Publishing Date:2025-08-15(First online date of this platform, not the publication date of the document)
Pages:3( 13-15 )